Pool has excess debris. Pool floor should be kept clean and free of debris.
4.0
General Comments
Wake County Plan Review and Recreational Sanitation Section recommends pools be hyper chlorinated at least twice a month. This activity should be accurately logged on the CPO check list form.
Pool has excess debris. Pool floor should be kept clean and free of debris.
4.0
16.
Fence had sections that has gaps greater than 4". This was fixed during inspection with chains and zip ties. Ensure that fencing remains adequate throughout the season, repair any damaged sections.
4.0
17.
Section of cracked concrete on the pool deck left of main gate is a potential tripping hazard. This should be smoothed out to prevent falls.
4.0
25.
Chemicals are not stored on site. Chemical room closed.
0.0
General Comments
Wake County Plan Review and Recreational Sanitation Section recommends pools be hyper chlorinated at least twice a month. This activity should be accurately logged on the CPO check list form.
An extra strainer basket for the pump is not provided. Flow meter is not operating properly; meter is full of sandy debris. Extra basket should be obtained and flow meter should be repaired.
4.0
25.
Light is not provided in the chemical closet. A light source should be provided.
2.0
30.
Over-the-rim spout is located in the deep end of the pool. Spout is not located under a diving board or within 6 inches of a handrail.
2.0
General Comments
Wake County Plan Review and Recreational Sanitation Section recommends pools be hyper chlorinated at least twice a month. This activity should be accurately logged on the CPO check list form.
17. clear deck and clean before opening. 15. all ring bouys provided must have 50' rope attached. 25. seperate chemical room not provided. Gates- locks at 54" with a total height of 66" fence- 67" chain link of 2 1/4"
need "ft" or "feet" in the pool next to the depth markers. Checks need to be done 3x a day. (As of 4:25 pm there were no checks) There were chemicals in the pump room.
safety rope provided but not hooked up. Need "ft" or "feet" near the deep end depth markers. Algae was around the fill spot on the pool deck. In the chemical room under the muriatic acid there was liquid --> is this water or acid?